Collaboration, abstraction, and other secrets of agile estimation

Collaboration, abstraction, and other secrets of agile estimation

Good estimation helps product owners optimize for efficiency and impact. That's why it's so important.

Estimation is hard. For software developers, it's among the most difficult–if not the most difficult–aspects of the job. It must take into account a slew of factors that help product owners make decisions that affect the entire team–and the business. With all that at stake, it's no wonder everyone from developers to upper management is prone to getting their undies in a bunch about it. But that's a mistake. Estimation is just that: an estimate. Not a blood-oath.
There's no requirement to work weekends in order to compensate for under-estimating a piece of work. That said, let's look at some ways to make estimates as accurate as possible.

Collaborating with the product owner

In agile development, the product owner is tasked with prioritizing the backlog–the ordered list of work that contains short descriptions of all desired features and fixes for a product. Product owners capture requirements from the business, but they don’t always understand the details of implementation. So good estimation can give the product owner new insight into the level of effort for each work item, which then feeds back into their assessment of each item's relative priority.
When the engineering team begins its estimation process, questions usually arise about requirements and user stories. And that's good: those questions help the entire team understand the work more fully. For product owners specifically, breaking down work items into granular pieces and estimates helps them prioritize all (and potentially hidden!) areas of work. And once they have estimates from the dev team, it's not uncommon for a product owner to reorder items on the backlog.

Agile estimation is a team sport

Involving everyone (developers, designers, testers, deployers... everyone) on the team is key. Each team member brings a different perspective on the product and the work required to deliver a user story. For example, if product management wants to do something that seems simple, like support a new web browser, development and QA need to weigh in because their experience has taught them what dragons may be lurking beneath the surface. Likewise, design changes require not only the design team's input, but that of development and QA as well. Leaving part of the broader product team out of the estimation process creates lower quality estimates, lowers morale because key contributors don't feel included, and compromises the quality of the software.
So don’t let your team fall victim to estimates made in a vacuum. It’s a fast track to failure!

Story points vs. hours

Traditional software teams give estimates in a time format: days, weeks, months. Many agile teams, however, have transitioned to story points. Story points rate the relative effort of work in a Fibonacci-like format: 0, 0.5, 1, 2, 3, 5, 8, 13, 20, 40, 100. It may sound counter-intuitive, but that abstraction is actually helpful because it pushes the team to make tougher decisions around the difficulty of work. Here are few reasons to use story points:
  • Dates don’t account for the non-project related work that inevitably creeps into our days: emails, meetings, and interviews that a team member may be involved in.
  • Dates have an emotional attachment to them. Relative estimation removes the emotional attachment.
  • Each team will estimate work on a slightly different scale, which means their velocity (measured in points) will naturally be different. This, in turn, makes it impossible to play politics using velocity as a weapon.
Teams starting out with story points use an exercise called planning poker. At Atlassian, planning poker is a common practice across the company. The team will take an item from the backlog, discuss it briefly, and each member will mentally formulate an estimate. Then everyone holds up a card with the number that reflects their estimate. If everyone is in agreement, great! If not, take some time (but not too much time–just couple minutes) to understand the rationale behind different estimates. Remember though, estimation should be a high level activity. If the team is too far into the weeds, take a breath, and up-level the discussion.

Estimate smarter, not harder

No individual task should be more than 16 hours of work. (If you're using story points, you may decide that, say, 20 points is the upper limit.) It’s simply too hard to estimate individual work items larger than that with a high degree of confidence. And that confidence is especially important for items at the top of the backlog. When something is estimated above your team's 16-hour (or 20-point) threshold, that's a signal to break it down into more granular pieces and re-estimate.
For items deeper in the backlog, give a rough estimate. By the time the team actually begins to work on those items, the requirements may change, and your application certainly will have changed. So prior estimates won’t be as accurate. Don’t waste time estimating work that is likely to shift. Just give the product owner a ballpark figure she can use to prioritize the product roadmap appropriately.

Learn from past estimates

Retrospectives are a time for the team to incorporate insights from past iterations–including the accuracy of their estimates. Many agile tools (like JIRA Software) track story points, which makes reflecting on and re-calibrating estimates a lot easier. Try, for example, pulling up the last 5 user stories the team delivered with the story point value 8. Discuss whether each of those work items had a similar level of effort. If not, discuss why. Use that insight in future estimation discussions.
Like everything else in agile, estimation is a practice. You'll get better and better with time.