A.   Entry Criteria:

All functionalities are successfully tested by dev team during Unit /Integration testing. All
High severity bugs has been fixed/closed those were founded in Unit/Integration testing.
Provided environment is stable for testing (Smoke test is passed)
Dev team has provided release note
Unit/Integration/Database testing has done by dev


B.   Exit Criteria:

All functionality has been tested according to the requirement
Defect rate is fall down to certain level
All requirements has been covered according to RTM or other metrics
All test cases have got passed status
Time is over
Budget is over

C.   Suspension/Resumption criteria:

Entry/Exit criteria is not meet
Smoke test is failed
Unavailability of any dependent system during testing
Project plan will be update accordingly requirement
Show Stopper (No work around)

Testing is resumed once a suitable fix has been delivered